231112002460 - THE APPLICATION TO RENEW THE ENVIRONMENTAL CLEARANCE CERTIFICATE THE OPERATION AND MAINTENANCE OF AN EXISTING 66KV GERUS – PARESIS TRANSMISSION LINE INCLUDING PARESIS SUBSTATION.

The ECC is for the operation and maintenance of an existing 66kV Gerus – Paresis Transmission line including Paresis Substation. In 2020, NamPower obtained the Environmental Clearance Certificate for the management and operation of the 66kV Gerus – Paresis transmission line. NamPower would therefore like to apply for the renewal of the ECC for 66kV Gerus – Paresis line in order to comply with the Environmental Management Act (Act 7 of 2007) and its regulations. This application will also include the Paresis Substation that was not previously included.

Prpject status APPROVED

For further information contact:

Ministry of Environment and Tourism

Department of Environmental Affairs

(+264 -61) 284 2701 (T)

(+264-61) 240 339 (F)

http://www.met.gov.na